Complex Site Remediation
EPS was engaged to complete the remediation and bulk earthworks of a large 55 hectare manufacturing facility. The works involved managing multiple contaminants across Category A to Category D soils, including asbestos-impacted soils, PFAS-impacted soils and water, lead-impacted soils, and hydrocarbon-impacted soils. The project was delivered within budget to a very time contstrained program and required close auditor involvement, a documented chain of evidence, and the execution of large-scale bulk earthworks.
Project Summary
Project Outcomes
Excavation and abatement of over 87,000m³ of asbestos-impacted material across the site. EPS undertook the classification and identification of more than 36 existing stockpiles, with each stockpile treated accordingly. Backfilling was completed under Level 1 conditions, with processing carried out to maximise the volume of soil suitable for reuse while meeting strict environmental and geotechnical parameters. The team successfully met the project timelines and delivered innovative solutions to overcome complex project constraints.
Abated material excavated: 87,534m³
Disposal: 9,833 tonnes of CAT A-CAT-C materials
VIC EPA, WorkSafe, landowner, developer, local community, local business, international business, subcontractors
Stakeholders
Duration
3 months
Location
Client Restricted
Industry
Manufacturing